Home

Building Upstairs (part 2)

Visual changes were gradual for week 9 through 18 [su_table] Week Starting 1 1-Jun-14 Floor beams and shutterboard installed 2 8-Jun-14 Walls with exterior cladding installed, roof rafters installed 3 15-Jun-14 Roof batons installed. Plumber and electrician start installing in walls and under floor stuff 4-8 22-Jun-14 – 20-Jul-14 Problems with steel structure 9-11 27-Jul-14 –

Building Upstairs (part 2) Read More »

Building Upstairs

1 June 2014 We’re adding a 2 bedroom unit on the top of our house. Many delays were experienced getting planning permission. Started working with the architect, Bryan Lee, in February 2013. The plans were finally approve in March 2014. Construction was due to start 1 May 2014. Then steel was not available so the framing

Building Upstairs Read More »